Secured Scaffolding
Product Description
|
Taking into account the scaffold erection project, the heights and positions of the lower adjustment shafts are adjusted. |
|
The starting legs are mounted on the adjustment shafts, the distances are clarified with horizontal connections and the system is leveled. |
|
In ranges with ladder platforms, the platforms are mounted on the starting legs. |
|
According to the project, the first row using cross-linking is created using the first module, board, horizontal connection and cross-linking. |
|
The first row completes the installation. |
|
Upper floor platforms (pay attention to the staircase detail) are assembled. |
|
According to the project, the second row using cross-linking is created using the first module, board, horizontal link and cross-link. |
|
The second row completes the installation and the heels are assembled. |
|
Scaffolding system is anchored to the facade according to the project. |
|
Installation continues in the same order according to the project. |